- CRA-5.6 CRA-5.6 Planned and Unplanned System Outages
- CRA-5.6.1- Licensees must have multiple communication channels to ensure that its clients are informed, ahead of time, of any outages which may affect them.Added: April 2019
- CRA-5.6.2- Licensees must have clear, publicly available, procedures articulating the process in the event of an unplanned outage. During an unplanned outage,- licensees must be able to rapidly disseminate key information and updates on a frequent basis.Added: April 2019
- CRA-5.6.3- Licensees should have a programme of planned systems outages to provide for adequate opportunities to perform updates and testing.Added: April 2019