RM-2.5.4

For purposes of Paragraph RM-2.5.3, if an instalment is missed on 1st March 2010, but payment is made on 1st April 2010 (and the March instalment is still not paid), then the credit facility will become over 90 days overdue by 1st June 2010, even if the April and May instalments are paid on time and in full, and a provision must at least be taken in respect of the overdue amount (but not necessarily the full outstanding amount of the credit facility if other payments were made).