GR-5.3.1

All new controllers or prospective controllers (as defined in Section GR-5.2) of a Bahraini specialised licensee must obtain the approval of the CBB. Any increases to existing controllers' holdings or voting control (as outlined under Paragraph BR-2.3.8) must also be approved by the CBB and are subject to the conditions outlined in this Section. Such changes in existing controllers (as defined in the Section GR-5.2) or new/prospective controllers of a licensee must satisfy the CBB of their suitability and appropriateness according to the criteria outlined in Paragraphs GR-5.3.2 to GR-5.3.5. The CBB will issue an approval notice or notice of refusal of a controller according to the approval process outlined in Section GR-5.4 and Paragraph GR-5.1.6.

Amended: April 2012
May 2011