CA-3.4.6

In the Istisna'a contract, the Islamic bank licensee assumes the completion risk12 that is associated with the failure to complete the project at all, delay in completion, cost overruns, occurrence of a force majeure event, and unavailability of qualified personnel and reliable seller(s) or sub-contractors, including any late completion penalty13 payable to the ultimate customer due to non-fulfilment of required specifications.


12 In conventional project financing, the completion risk is normally borne by the project sponsor/contractor, and not by the bank, because the project sponsor/contractor has most often been asked to provide an undertaking to cover cost overruns.

13 Normally, the contract between the bank and the contractor will specify in a penalty clause the latter's liability for penalties in case of delays for which it is responsible.